Step 1 (Pre-Cleaning): Disconnect the return pipes of the boiler and connect the hoses of the machine. The machine is switched on without heating. Thus, the system is pre-cleaned.
Step 2 (Drug Disinfection): Contaminated clean water in the sanitary warehouse. The heating system is started. The ideal temperature is between 40 ° C and 50 ° C. The circulation system continues until cleaned.
Step 3 (Rinse): After the system has been cleaned, the machine is emptied of the tank and filled with fresh water. Circulation with clean water is carried out and the process is terminated. Finally, add water to the system and make it ready for operation. Remember to take the air of the radiator and installation.